UPDATE - GRAND RAPIDS (WZZM) - The construction that will close the intersection of Fulton and Monroe has been delayed until Friday, February 24.
GRAND RAPIDS (WZZM)- You will need to plan another way through part of downtown Grand Rapids beginning Wednesday.
The intersection at Fulton and Monroe will close for three weeks so crews can repair utility ducts and street lights. The intersection will temporarily reopen with one lane heading in each direction beginning March 30th.
This is the first phase of a five phase project for Fulton Street. The second phase will close the intersection at Fulton and Ottawa beginning March 15th. The sidewalks will stay open during the work.
Construction should be finished by May.
Top Grand Rapids Central Stories
Upcoming Events near Grand Rapids Central
Most popular stories from nearby communities

Do you have a story to tell? Become a community blogger!
Community Sponsors
Grand Rapids Central Real Estate Listings
|
$59,900
Courtesy of: Keller Williams Realty
|
$319,900
Courtesy of: Keller Williams Realty
|